Investing in renewable energy projects not only provides an opportunity to create a positive environmental impact but also to achieve solid financial returns. At The Green Power of Brazil, we work with carefully selected initiatives, ensuring that each project presents realistic yield projections and detailed risk assessments.

Project Development Milestones

The Green Power of Brazil

Land Research and Contract

Land Research and Contract

Conducted comprehensive research on the land required for the project, including property ownership, legal considerations, and all necessary contracts or agreements.
Connection Data Gathering

Connection Data Gathering

Basic Engineering Studies

Basic Engineering Studies

Carried out preliminary engineering assessments, including site surveys, soil testing, and feasibility analyses to establish the technical viability of the project.
Preliminary Water Grant

Preliminary Water Grant

Obtained necessary water-related grants and permits to ensure the project has legal access to the required water resources.
Topographic Studies

Topographic Studies

Conducted detailed topographic surveys to understand the terrain and landscape features of the project site, which have informed the design and construction process.
Preliminary Environmental Authorization

Preliminary Environmental Authorization

Obtained the necessary preliminary environmental approvals and permits to ensure the project's compliance with environmental regulations.
Suppression Authorization

Suppression Authorization

Obtained authorization to remove native vegetation in the area needed for construction.
Environmental Authorization

Environmental Authorization

Completed the full environmental authorization process, including impact assessments and all necessary mitigation measures to replenish and preserve the local fauna and flora.
Installation Approval and Construction

Installation Approval and Construction

Projects ready to initiate construction phase upon securing investment;
Start of Operation

Start of Operation

In 2 years the plant will be running and generating energy revenue.